Construction Progress Updates
August 15, 2026
- Block masonry in progress at levels: 0.00 (1st floor), +3.30 (2nd floor, +6.60 (3rd floor) +9.90 (4th floor)
- Block masonry work on the 1st floor is 80% complete
- Block masonry work on the 2nd floor is 80% complete
- Block masonry work on the 3rd floor is 50% complete
- Block masonry work on the 4th floor is 75% complete