Construction Progress Updates
October 15, 2026
-
Blockwork is ongoing at the following elevation levels: +6.60 (3rd floor), +9.90 (4th floor), +13.20 (5th floor), and +16.50 (6th floor)
-
1st floor: 100% of blockwork completed
-
2nd floor: 100% of blockwork completed
-
3rd floor: 95% of blockwork completed
-
4th floor: 95% of blockwork completed
-
5th floor: 95% of blockwork completed
-
6th floor: 95% of blockwork completed
MEP works are ongoing:
-
Installation of vertical ventilation ducts within the shafts - 90% completed
-
Installation of vertical drainage pipes within the shafts - 90% completed