Construction Process
Block A13

Time left in phase 1:

Construction Progress Updates

October 15, 2026

  • Blockwork is ongoing at the following elevation levels: +6.60 (3rd floor), +9.90 (4th floor), +13.20 (5th floor), and +16.50 (6th floor)

  • 1st floor: 100% of blockwork completed

  • 2nd floor: 100% of blockwork completed

  • 3rd floor: 95% of blockwork completed

  • 4th floor: 95% of blockwork completed

  • 5th floor: 95% of blockwork completed

  • 6th floor: 95% of blockwork completed

MEP works are ongoing:

  1. Installation of vertical ventilation ducts within the shafts - 90% completed

  2. Installation of vertical drainage pipes within the shafts - 90% completed