Construction Process
Block A13

Time left in phase 1:

Construction Progress Updates

September 15, 2026

  • Block masonry is in progress: 0.00 (first floor) +3.30 (second floor) +6.60 (third floor) და +9.90 (fourth floor) +13.20 (fifth floor) +16.5 (sixth floor) at elevations
  • Block masonry works on the first floor completed: 100%
  • Block masonry works on the second floor completed: 100%
  • Block masonry works on the third floor completed: 95%
  • Block masonry works on the fourth floor completed: 95%
  • Block masonry works on the fifth floor completed: 95%
  • Block masonry works on the sixth floor completed: 95%
  • MEP works are in progress:
  • 1. Installation of vertical ventilation ducts in shafts - Completed: 90%
  • 2. Installation of vertical drainage pipes in shafts - Completed: 90%