Construction Process
Block B1

Time left in phase 1:

Construction Progress Updates

June 15, 2026

  • The concrete structure of the slab and columns at elevation +22.98 m (eighth floor) has been completed.

  • Blockwork construction has commenced at elevations -0.12 m (first floor)+3.18 m (second floor), and +6.48 m (third floor).

  • 90% of the blockwork has been completed on the first floor.

  • 30% of the blockwork has been completed on the second floor.

  • 70% of the blockwork has been completed on the third floor.