Construction Process
Block B1

Time left in phase 1:

Construction Progress Updates

August 15, 2026

  • Block masonry in progress at levels: 0.00 (1st floor) +3.30 (2nd floor, +6.60 (3rd floor) +9.90 (4th floor) + 13.20 (5th floor)
  • Block masonry work on the 1st floor is 95% complete
  • Block masonry work on the 2nd floor is 95% complete
  • Block masonry work on the 3rd floor is 85% complete
  • Block masonry work on the 4th floor is 85% complete
  • Block masonry work on the 5th floor is 60% complete

     

Tbilisi Acres
B1

Request a call back

Please complete the request form to have us call you.
By submitting you are agreeing to our Terms and Conditions.