Construction Process
Block B5

Time left in phase 1:

Construction Progress Updates

June 15, 2026

  • Reinforcement works for the slab at elevation +19.68 m (seventh floor) have commenced

  • Blockwork construction has commenced at elevations -0.12 m (first floor) and +3.18 m (second floor)

  • 60% of the blockwork has been completed on the first floor

  • 90% of the blockwork has been completed on the second floor