Construction Progress Updates
September 15, 2026
- Block masonry in progress at levels: +6.60 (3rd floor) +9.90 (4th floor) +13.20 (5th floor)
- Block masonry work on the 1st floor is 100% complete
- Block masonry work on the 2nd floor is 100% complete
- Block masonry work on the 3rd floor is 95% complete
- Block masonry work on the 4th floor is 60% complete
- Block masonry work on the 5th floor is 50% complete