Time left in phase 1:
Construction Progress Updates
August 15, 2026
- Block masonry in progress at levels: 0.00 (1st floor) +13.20 (5th floor)
- Block masonry work on the 1st floor is 95% complete
- Block masonry work on the 2nd floor is 100% complete
- Block masonry work on the 3rd floor is 100% complete
- Block masonry work on the 4th floor is 100% complete
- Block masonry work on the 5th floor is 85% complete
