Construction Process
Block B2

Time left in phase 1:

Construction Progress Updates

August 15, 2026

  • Block masonry in progress at levels: 0.00 (1st floor) +13.20 (5th floor)
  • Block masonry work on the 1st floor is 95% complete
  • Block masonry work on the 2nd floor is 100% complete
  • Block masonry work on the 3rd floor is 100% complete
  • Block masonry work on the 4th floor is 100% complete
  • Block masonry work on the 5th floor is 85% complete