Time left in phase 1:
Construction Progress Updates
September 15, 2026
- Block masonry is in progress: 0.00 (first floor) +3.30 (second floor, +6.60 (third floor) +9.90 (fourth floor) + 13.20 (fifth floor) +16.5 (sixth floor) +19.8 (seventh floor) at elevation
- Block masonry works on the first floor completed: 95%
- Block masonry works on the second floor completed: 100%
- Block masonry works on the third floor completed: 100%
- Block masonry works on the fourth floor completed: 100%
- Block masonry works on the fifth floor completed: 95%
- Block masonry works on the sixth floor completed: 80%
- Block masonry works on the seventh floor completed: 50%
