Reserve by November 20!

Construction Process
Block A10

Time left in phase 1:

Construction Progress Updates

October 15, 2026

  • Concreting of vertical columns and walls is ongoing at elevation level +13.40

  • Blockwork is ongoing at elevation level 0.00 (1st floor)

  • 1st floor: 80% of blockwork completed